The Pipeline is 30" in diameter and was approx 2000' in length, 800' under water, with approx. 50 sections mated together with the use of an underwater hydro-pull.
The pipe started on shore and the wooden intake crib (pictured) at the end was in 80' of water.
The dive team consisted of 5 divers and completed the project in about 4 weeks.